Rigging Plan

November 21, 2008

Rigging Plan Worksheet

 

Site of Installation:  New Hampshire                                                Job#:  9653

 

Mobile Crane Operations:

Please find the attached drawing inclusive of Tri-Lift TL150 capacities and load charts.

 

Blocking:                                                                                                                               

Oak hardwood.  (If Required.)

 

Total Weight of Lift:

70,000 lbs.

 

Description of Material to be Lifted:

Solar, Gas Turbine.  8’11” x 32’ x 7’ 10 ¼”

 

Pre-lift Meeting:

CIC Lead Person Tom Canady, CIC Crew (3) Ron Cote, Larry Scarborough, Tom Dart.  CIC management representative to document meeting.

 

Designated Signal Person: 

Tom Canady

 

Designated Person in Charge/OSHA Safety Check:

Tom Canady

 

Communication and Signals:

Hand signals.

 

Method of Accomplishment:

  1. Warehouse to Truck:
    1. Please refer to the attached diagram:  (The diagram shows only one side of the turbine.)

                                                               i.      The turbine will be shackled to the tri lift using the four pick points provided by the manufacturer.

                                                              ii.      To ensure an even pick one side of the turbine will have an additional 1’ of sling used.

                                                            iii.      The Tri-Lift will lift the turbine.

                                                            iv.      A multi axle trailer will back in and the turbine will be placed for transportation.

1.       All appropriate binders will be used to secure the load.

 

 

 

 

  1. Truck to Turbine Pad:
    1. The same hoisting plan as above will be used for the unload and placement.
    2. The Tri-Lift will be placed inside the building.
    3. The multi axle trailer will back into the building
    4. Using the above stated plan the turbine will be lifted off the trailer.
    5. The trailer will pull out of the building.
    6. The Tri-Lift will lower the turbine to a lower transport level.
    7. The Tri-Lift will move forward and set the turbine for final placement.

June 18, 2008

Chicopee Industrial Contractors would like to congratulate the Boston Celtics on their 17th NBA Basketball Championship.  The Celtics epitomize unselfish team play.

When it comes to unselfish team play in the world of industrial contracting, Chicopee Industrial Contractors (CIC) is the undisputed champion.  Whether your needs are rigging, millwrights, construction, or temporary plant maintenance, CIC is “The Permanent Solution to Your Temporary Problems.”  Like the Celtics our crews demonstrate a total commitment to team play and a winning attitude in serving the customer’s needs.

Herman Melville wrote, “We cannot live for ourselves alone.  Our lives are connected by a thousand invisible threads, and along these sympathetic fibers, our actions run as causes and return to us as results.”  We are new to the blogging world and we look forward to sharing our successes, our trials and tribulations and those unique stories that define who we are as a company and who we are as human beings.  It is our hope that our actions will run as causes and return to us as results. 

Follow

Get every new post delivered to your Inbox.